Follow Us: 

Coal Truck Loadout Facility

Kiewit Mining

Haystack, WY



The Haystack Coal Company Truck Loadout project was a joint project between Kiewitt Mining and R&M Engineering. R&M did the feasibility study, and then later was awarded the design contract. We worked with the equipment manufactures to get and evaluate bids for the various conveyors and other pieces of equipment. We also designed the structural steel and support foundations for these pieces of equipment and enclosures.


3D Model:


A 3D analytical model was constructed in Risa 3D where it was subjected to all viable loads and analyzed for strength. This same model was then transferred to Autodesk's Revit (which is what you see in the video below) to facilitate connection design, construction drawings, and to give our clients an isometric view of the final product.


Services Provided:

  • Facility Layout
  • Truck Loading
  • Project Cost Estimate
  • Steel Structure Design
  • Concrete Foundation Design